View the latest construction status update here.
Mt. Airy Community Development Corporation continues to work with City and State elected officials to create a best-in-class recreation amenity at Simon’s Rec Center. This top-tier youth athletic campus will provide NW Philly’s neighborhoods with a premiere public sports and recreation center, designed to serve the area for decades to come. It will also serve as the City’s athletic campus prototype, providing tangible proof of the viability, impact, and potential of future recreation, sports, and community assets as safe spaces for the enjoyment of children and community members.
Simons Recreation Center currently enrolls 700+ children per year in sports programs and is heavily used by low- and moderate-income communities, where health disparities and limited access to green space are known issues.
Our project involves extensive new construction and renovations including: a new 400-meter, 6-lane running track with a synthetic turf multi-purpose field for football, soccer and lacrosse on the infield, complete with stadium seating, a press box, stadium lighting and public address system; a new 24,000-square-foot gymnastics and boxing center with storage; and new little league and softball fields complete with seating, press boxes, stadium lighting and public address system.
The renovation also features a new tennis court with lighting; a new cheer practice area with safety surface and lighting; a new playground and splash ground; a new adult exercise station; a renovated handball court with lighting; and a new quarter-mile plus walking path. Multiple underground structures including a new stormwater management system with two subsurface infiltration systems are hidden beneath the site.
Additional enhancements include a new 1,100 square foot storage building; renovations to the existing storage building; new masonry stairway pedestrian site entrances; new signage; a new changing room building for athletes; a new public bathroom building; a new exterior dining area with furniture; renovated site perimeter retaining walls; new underground electrical system; new fencing; and new landscaping.
The City of Philadelphia is supplementing the renovation with an additional project, which includes: renovations to the existing recreation center and concessions building; new sidewalks; videotron scoreboards; renovated basketball courts; a new STEM/ESports lab; new site security; and site-wide Wi-Fi. Several exterior murals will also beautify the site.
| TYPE: | New Construction + Renovation |
| USE: | Recreation |
| DEVELOPMENT CONFIGURATION: | -11.91 acre site -New Construction of Buildings: 24,000 square foot Gymnastics & Boxing Center, Storage Building (1), Locker Room Building (1), Rest Room Building (1), Press Boxes (3) -New Construction of Playing Fields & Site Amenities: Synthetic Turf Multi-Sport Field – football, soccer, lacrosse (1), 6-lane running track (1), Little League field (1), Softball field (1), Tennis Court (1), Cheer Practice Area (1), Playground (1), Splash Pad & Sprayground (1), Walking Path (1), Adult Exercise Area (1), LED Field Lighting, 25,000 square foot Stormwater Management Underground Infiltration Basin -Renovations to Playing Fields & Site Amenities: Handball Court (1), Storage Building (1), Concession Building (1), Site Perimeter Stairways and Retaining Walls, Security System, Parking, Landscaping |
| MT. AIRY CDC INVOLVEMENT: | -Community Engagement -Construction Contract Lifecycle Management: Planning & Project Setup; Tendering & Bidding; Bid Evaluation & Contract Award; Contract Drafting, Writing & Execution; Change Orders and Scope Adjustments; Progress Payments -Team member for Construction Administration -Support Design Team -Capital Project Manager |
| FINANCING: | -City of Philadelphia Capital Funds -City of Philadelphia Council District 9 Capital Funds -Grant – Pennsylvania Redevelopment Assistance Capital Program (RACP) administered by the Office of the Budget (OOB) of the Commonwealth of Pennsylvania |
| PROJECT TEAM: | Mt. Airy Community Development Corporation Capital Program Office – City of Philadelphia Parks & Recreation – City of Philadelphia Daniel J. Keating Construction – General Contractor Langan Engineering and Environmental Services, Inc. – Landscape Architect & Civil Engineer Heckendorn Shiles Architects – Architect Pennoni Associates Inc. – Civil & Geotechnical Design O’Donnell & Naccarato – Foundation Design SITIO – Architect SRW Engineering & Architecture – Mechanical, Electrical & Plumbing Engineer Rodriguez Consulting – Surveyor Hunt Engineering Company – Special Inspections David Mason Associates – Structural Engineer InFocus Planning – Playground & Spray Park Design ENFRA Solutions – Mechanical & Plumbing Design Carr & Duff – Electrical Design Holstein-White – Electrical Design & Engineering EMMS Electrical – Interior Electrical Design Oliver Fire Protection & Security – Fire Suppression System Design Applied Video Technology – Audio Visual Design |