Mt. Airy CDC is managing a major upgrade at Simons Recreation Center in West Oak Lane. We are working with City and State elected officials to create a top-tier youth athletic campus. View the full project overview here.

Late Summer 2026 Project Status

Over the past month, the Simons Recreation Center property continues to be a highly active construction site, with substantial progress being made.

  • The entire site, including the Recreation Center, remains closed to the public.
  • Installation of building systems and interior finishes for the new locker room and bathroom buildings adjacent to Rodney Street is nearing completion.
  • Preparations are complete for the renovation of the existing concession building, and work will commence shortly.
  • Work on the site entrances continues to advance, and replacement of the stairs at Walnut and Rodney is on-going.
  • The site’s field electrical work is nearing completion.
  • Installation of the interior fencing is nearing completion.
  • Installation of the track top coating is complete; following a cure period, track striping will commence.
  • Work is nearing completion on bringing the utilities to the press boxes and to the storage shed located adjacent to the synthetic turf field.
  • Installation of the bleachers on the concrete pads adjacent to the little league and softball fields is now complete.
  • Softball and little league field fence systems have been installed, and backstop fencing is scheduled for delivery.
  • The Throwing pad system for discus and shot put has been installed.
  • Site electrical connections to the Recreation Center are nearing completion.
  • Installation of the splash park plumbing is nearing completion.
  • Fine grading of topsoil together with grass seeding of select areas is ongoing.
  • Planting of a portion of the new trees is ongoing and is nearing completion.
  • Installation of the binder course/base course of asphalt on top of the subbase course of stone for the new walking path is now complete. Installation of the surface course of asphalt is nearing completion.
  • Fine grading and seeding of the little league and softball fields is complete.
  • The base course of the infields of the little league and softball fields is nearing completion.
  • Design of the new score and video boards for the little league field, softball field and synthetic multisport field and running track is completed, and fabrication has commenced.
  • Work has commenced on the new boxing and gymnastics building and the associated reconfiguration of the tennis courts and cheer area. 
  • Installation of the new boxing and gymnastics building’s foundations is complete.
  • Renovation of the Recreation Center interior is progressing including the following:
    • New flooring. 
    • New LED lighting.
    • New paint.
    • New rec center lobby desk.
    • New food service kitchen renovation, new residential range, stainless steel countertops, millwork and finishes.
    • Hockey and public restroom ADA grab bars, accessories, and finishes.
    • New ADA-compliant drinking fountains.
    • New hockey concessions, kitchen renovations, new residential range, stainless steel countertops, millwork and finishes.
    • Ice rink repairs, heaters. and bleachers.
    • New ice rink fire protection system.
    • New gymnasium scoreboard, lighting, floors resealed, and bleachers.
    • Resealing the gymnasium floor. 
    • New exterior doors.
  • Design is nearing completion for the Recreation Center’s STEM/ESports lab.  
  • Planning is nearing completion for the various murals to be painted on the site’s perimeter retaining walls, buildings and basketball courts.

Substantial project completion is expected at the end of the 2026 calendar year.